Data Centers

Data Center Construction, Acharnon Uptime Requirements Upgrade (HTO)

Client : OTE

Location : Athens , Acharnon Data Center

Year : 2019

Description :

The construction project regarded what was the Electromechanical equipment upgrade of one of HTOs main data centers in Athens. The works included electrical panel installation and replacement of existing , new rack installation , metering equipment and interconnection with newly installed generator sets including both hydraulic and electrical connections. All the works undertaken was while the building was functional which added to the difficulty of the project.

Data Center Construction , DC RENTI (HTO)

Client : OTE

Location : Athens , Renti Data Center

Year : 2016

Description :

The project included the construction of a new data center of capacity 1.5 MW. The construction phase included the preparation of the existing space (demolition works and renovation of space) , installation of all the E/M equipment , Flooring Equipment, Yellow Ducts and all the relevant and required monitoring and controlling modules.

Data Center E/M Infrastructure Upgrade

Client : Vodafone

Location : Athens , Metamorfosi MTX Data Center

Year : 2020

Description :

The construction project included the works. that entailed the preparation of the data center and the building's infrastructure for the installation of 2 generator sets.

Data Center E/M Infrastructure Upgrade

Client : Vodafone

Location : Athens , Kalochori Data Center

Year : 2020

Description :

Data Center E/M Infrastructure Upgrade

Client : Vodafone (Ex- Cyta)

Year : 2021

Location : Metamorfosi , Athens.

Description : The project aimed at increasing the facility's energy capacity and autonomy by upgrading its overall Electrical Load Capability and its associated equipment (EV Panels , Bus Bars etc) as well. as the installation of 2 Soundproof Generator Sets able to handle the building's Load.

Data Center E/M Infrastructure Upgrade [BoG]

Client : Bank Of Greece

Location : Athens , Greece

Year : 2021 / 2022

Description :

The project regards the total reconstruction of Bank Of Greece data center. The IT space upgraded houses the equipment that handles the electronic security market and the undergoing construction will be responsible for the installation of Access Systems , UPS systems, Power Management Infrastructure , IT equipment , Cooling and Other.

Data Center E/M and IT Equipment

Client : Wind

Year : 2020

Location : Athens , Greece

Description :

The new data center segment was created in order to house the new IT equipment that will handle the exceed capacity required to move on to the 5G network technology.

Data Center Construction [BoG]

Client : Bank Of Greece

Location : Athens , Greece

Year : 2021 / 2022

Description :

The project regards the total reconstruction of Bank Of Greece data center. The IT space upgraded houses the equipment that handles the electronic security market and the undergoing construction will be responsible for the installation of Access Systems , UPS systems, Power Management Infrastructure , IT equipment , Cooling and Other. The new DC is designed with expandability in mind and allows for the increase of the Data Center's Capacity only by increasing its key components modules.